Songa Product and Chemical Tankers IV AS v Gardsea Shipping Inc (the MT Songa Coral) [2026] EWHC 1559 (Comm)
The Court considered whether a payment obligation under a Saleform 2012 MOA expired at midnight in (i) Norway, where payment was to be effected, or (ii) in the most westerly jurisdiction referred to in the MOA definition of "Banking Days". The Court held that the definition of "Banking Days" merely identified which calendar days counted for the purpose of calculating time and did not determine when a day began or ended. Buyers were required to release the purchase price from escrow by midnight in Norway and were in default when they failed to do so.
CIT Group Finance (Ireland) Unlimited Company v SpiceJet Limited [2026] EWHC 1277 (Comm)
Following SpiceJet's failure to satisfy payment obligations under Early Termination Agreements ("ETAs") entered into after aircraft lease payment defaults, the Commercial Court held that the lessor was entitled to render the ETAs null and void and revert to its remedies under the original leases. Rejecting arguments based on estoppel, waiver and reasonableness, the Court found that redelivery acceptance certificates issued under the ETAs did not prevent the lessor from pursuing lease-based claims arising from the lessee's earlier defaults.
Asghar v Patel [2026] EWHC 396
In a dispute as to the construction of a contract, the unsuccessful defendant sought to appeal the arbitration award under s.69. The claimant contended that the contract was oral, and thus the challenge was as to a matter of fact (to which s.69 is inapplicable). Dismissing the claimant’s argument, the Court found that whilst initially oral, the agreement was later reduced to writing such that s.69 was applicable, and that the Arbitrator had erred on the point of construction, such that the award would be set aside.
G2 Ocean AS v Tokio Marine Brasil Seguradora SA [2026] EWHC 997
Two Congenbills specified that freight was payable as per a C/P dated 12 June 2024 and contained the standard clause incorporating all terms and conditions including law and arbitration of “the charterparty dated as overleaf”. There was no such C/P but the Court ruled that 2 booking notes of that date (issued by Owners and covering the same amount of cargo as specified in the B/Ls) were incorporated. As these contained a London Arbitration clause (and despite the 1 year time bar having elapsed) , the Court issued an ASI restraining cargo insurers from continuing their damage claim in the Courts of Brazil.
Trans Trade v Sebat Shipping (the “Sebat”) [2026] EWHC 950 (Comm)
A voyage C/P provided that in the event of berth unavailability, NOR could be tendered from any usual waiting place. The Vessel tendered NOR at the pilot station some hours before anchoring at a usual place. The Tribunal held that an otherwise valid but premature NOR (as here) was deemed served on commencement of cargo operations. On appeal, the Court ruled that in the absence of waiver of the invalidity, the “Happy Day” ruling was inapplicable and thus the ship was never an arrived ship, and laytime never commenced.
Finco International AG v Integra Petrochemicals AG [2026] EWHC 727
Integra sold a quantity of MTBE to Finco, delivery ex-ship ARA (in the event Amsterdam) within a specified 14 day window. By agreement, ex-ship was changed to CIF. Finco alleged repudiatory breaches by Integra on the bases that neither was the nominated ship, “Aramon”, suitable for the Amsterdam facility, nor was the cargo delivered within the agreed window, and sought recovery of their LC payment. The Court ruled that (a) Finco’s stance on suitability of “Aramon” was equivocal such that they could not rely on a repudiatory breach and (b) once changed to CIF, by reason of incorporated BP GTCs, the delivery window was no longer a strict one, such that late arrival did not constitute a repudiatory breach either.