Case Summaries

Join our Case Summary Mailing List

Want to receive our weekly Case Summary direct to your inbox? Click below!

Commercial Court Louise Glover Commercial Court Louise Glover

Fehn Schiffarhts GMBH & Co KG v Romani Spa [2018]

“Owners challenged an arbitration award which held them liable to charterers in damages representing loss of value of the cargo following unauthorised fumigation. After the damage, receivers had assigned rights to charterers. If, as appeared, that assignment had been the basis of the tribunal's ruling, they had erred in law in not first making any finding that the receivers had sustained loss (an assignee not being able to acquire rights greater than those of the assignor); if charterers in their own right had suffered the loss (as alternatively argued), this too was not apparent from the award, which the Court ordered should be remitted to the tribunal for further consideration.”

Read More
Arbitration Louise Glover Arbitration Louise Glover

London Arbitration 15/18

“The Tribunal found that Sellers had exceeded the contractually specified period of delay, such that Buyers were entitled to terminate a shipbuilding contract and recover the instalments advanced; The Tribunal rejected Sellers' contentions for an implied term as to mutual co-operation and non-impeding, or the application of the 'Prevention Principle' on the grounds that the sophisticated express terms left no room for such provisions.”

Read More
Commercial Court Louise Glover Commercial Court Louise Glover

Deep Sea Maritime Ltd v Monjasa A/S (The Alhani) [2018]

“In an important case relating to the Hague Rules, the High Court ruled that (i) the Art III rule 6 one year time bar applies to claims for wrongful delivery (as well as claims for failures in the carriage of the cargo); and (ii) that such time bar is not interrupted by proceedings brought in a jurisdiction other than that stipulated, even if the Claimant did not have actual knowledge of the jurisdiction provision.”

Read More
Commercial Court Louise Glover Commercial Court Louise Glover

P v Q [2018]

“A long chain included 'middle' voyage charters (P/Q, Q/R, R/S) each with a clause imposing a time bar unless claims were notified and an arbitrator appointed within 13 months of final discharge. A cargo damage claim was brought against head owners after 11 months. Notice of an indemnity claim reached 'P' on the last day of the 13 month period remained unseen until the following day, so that notice to 'Q' and so on down the line was delayed. The Court construed the clause literally and strictly, rather than in the light of the chain. It also declined to extend P's time under s.12 of the Arbitration Act because although the circumstances were outside the reasonable contemplation of the parties, P did not act expeditiously and in a commercially appropriate fashion viz a viz Q.”

Read More
Commercial Court Louise Glover Commercial Court Louise Glover

Grindrod Shipping PTE LTD V Hyundai Merchant Marine Co. LTD [2018]

“Time charterers Grindrod had delayed for more than 6 years in pursuing their London arbitration claim for damages against owners and in the meantime the contractual time bar passed. The Tribunal issued an award, dismissing the claim on the grounds of an inordinate and inexcusable delay. The High Court dismissed Grindrod's 'serious irregularity' challenge to the award, pursuant to S.68 of the Arbitration Act , on the grounds that the complaint was one of form rather than substance (submissions raised and responded to under one heading had been addressed under another) and therefore there had been no breach of duty by the Tribunal nor any substantial injustice.”

Read More
Supreme Court Louise Glover Supreme Court Louise Glover

Rock Advertising Ltd v MWB Business Exchange Centres Ltd [2018]

“The Supreme Court held that the No Oral Modification (NOM) provision in a contract for occupation of office premises deprived a subsequent alleged oral agreement of any binding force as a contract variation. Parties who orally agree to the terms of a variation of the substance of their contractual relationship do not thereby impliedly agree to dispense with the NOM clause.”

Read More